How Boeing Will Get the 737 MAX Flying Again

Watch Facts Elle's

Key takeaways

- Boeing faced the task of returning nearly 800 grounded or undelivered 737 MAX aircraft to service following the March 2019 grounding. The fleet included 387 previously operating aircraft and approximately 400 jets Boeing continued manufacturing over the next nine months.

- Boeing’s effort to avoid expensive pilot training contributed to the development of MCAS, the system implicated in two fatal crashes. The MAX was marketed as requiring existing 737 pilots just two days of computer-based instruction, but simulator training was subsequently expected to become mandatory.

“The entire MAX aircraft was designed around assuring that pilots would not need simulator training.”

- Only 34 MAX simulators existed worldwide, creating a major obstacle to returning the fleet to service. Training 5,000 pilots for ten hours each would take approximately two months even with every simulator operating continuously, while the machines themselves could cost up to $15 million apiece.

- Large airlines and simulator owners held a significant advantage over smaller carriers competing for pilot training. South Korea’s Eastar Jet lacked its own simulator, while Fiji Airways owned one and could sell training time to other airlines; commercial training centers were expected to prioritize major customers.

“Many of these smaller airlines are going to be at the end of a long list to get their pilots trained.”

- FAA approval would begin another lengthy process rather than immediately restore MAX operations. Following certification flights and training evaluations, airlines would need to satisfy an airworthiness directive, complete modifications, and prepare aircraft that had been parked for months.

“This is where the real work begins.”

- Preparing each grounded MAX for service could take two weeks, while clearing Boeing’s undelivered aircraft backlog could take approximately one year. Airlines needed extensive inspections, cleaning and software updates, potentially diverting mechanics from other aircraft maintenance.

- Passenger resistance threatened the MAX’s commercial recovery even after regulatory approval. A commissioned survey found 70% of American travelers intended to avoid the aircraft, while online booking systems made identifying and choosing alternative aircraft easier than during previous safety groundings.

“Boeing has to persuade regulators it can fly, and then it has to persuade the public it can fly.”

- Boeing planned to monitor passengers’ social media complaints and alert flight crews when travelers expressed anxiety about the MAX. Its proposed reassurance campaign also included direct digital responses, printed safety cards and explanatory videos, reflecting the commercial risk that frightened passengers could discourage airlines from operating or purchasing the aircraft.

All points

1976 words

- Boeing’s 737 MAX was grounded worldwide in mid-March 2019. The grounding followed two fatal crashes involving a flight-control system that could respond to incorrect sensor information by commanding the aircraft’s nose downward.

- The grounding damaged Boeing’s reputation for safety and reliability. The 737 MAX was the newest generation of Boeing’s most popular aircraft family, making its problems particularly damaging to the company.

- The grounding affected the wider American economy and global aviation industry. Boeing was one of the United States’ largest companies and employers, while airlines worldwide lost aircraft during a period of sustained industry growth.

- A total of 387 operational 737 MAX aircraft were grounded. These aircraft had already entered airline fleets and were flying commercially before regulators suspended their operations.

- Boeing continued manufacturing the MAX for nine months after the grounding. Approximately 400 additional aircraft were assembled but remained undelivered, occupying available parking space around Boeing’s factories.

- Nearly 800 aircraft would eventually need to be returned to operational service or prepared for delivery. This included both previously operating aircraft and newly manufactured jets awaiting completion.

- Extended aircraft storage created a separate engineering problem. Commercial aircraft normally operate almost daily, apart from maintenance periods. Some MAX aircraft were expected to remain parked for more than a year before returning to service.

- Regulatory approval alone would not restore the MAX fleet. Boeing needed approval of its technical fixes, airlines needed to prepare aircraft and pilots, and passengers needed sufficient confidence to board the aircraft.

- Boeing initially expected the grounding to last only weeks. After the March 2019 grounding, the anticipated return date was repeatedly postponed.

- Boeing’s projected return date had shifted to mid-2020. At the time of the video's production, this remained an uncertain forecast rather than an approved schedule, with further delays considered possible.

- The final technical solution had not yet been established. Boeing needed to resolve the problems associated with the two crashes as well as additional issues identified during subsequent investigations.

- The FAA would conduct a certification flight after Boeing finalized its proposed modifications. Boeing would supply a 737 MAX fitted with the necessary hardware and software changes, and Federal Aviation Administration pilots would evaluate the aircraft in flight.

- An analysis period of several days was expected after the certification flight. If the modifications performed satisfactorily, the process would advance to an evaluation of pilot training requirements.

- The Joint Operations Evaluation Board would determine what training returning MAX pilots required. This FAA-run group, composed primarily of 737 MAX pilots from different countries, would test the modifications in flight simulators.

- The Joint Operations Evaluation Board’s evaluation was expected to take approximately two weeks. Its recommendations would then be passed to the FAA’s Flight Standardization Board for incorporation into a formal report.

- Mandatory simulator training was expected to become a major obstacle to the aircraft’s return. Boeing itself was expected to recommend simulator training, making it likely that the FAA would require pilots to complete it before operating the MAX again.

- The 737 MAX had originally been designed to avoid mandatory simulator training. Boeing wanted existing 737 pilots to transition to the new aircraft without the expense of extensive additional instruction.

- Boeing marketed the MAX as requiring only two days of computer-based training for existing 737 pilots. This was an important commercial advantage because pilot training adds substantial costs for airlines.

- The desire to preserve familiar 737 handling characteristics contributed to the development of MCAS. The system was intended to make the MAX behave like previous 737 models despite aerodynamic differences that otherwise required electronic intervention. MCAS subsequently became central to the two crashes.

- Boeing’s original training strategy left the industry with very few MAX simulators. Because the aircraft was not expected to require extensive simulator instruction, demand for the equipment had been limited.

- Only two companies manufactured 737 MAX flight simulators: CAE and TRU Simulation. Their specialized equipment had to reproduce the aircraft’s flight characteristics accurately enough for certified pilot training.

- A full-motion 737 MAX simulator could cost as much as $15 million. The machines were almost as expensive as some aircraft, and operating costs could run into thousands of dollars per hour.

- Simulators were expensive but still offered an economic advantage over training in actual aircraft. Using a real airliner for training created additional operating costs, including fuel, provided that a sufficiently accurate simulator was available.

- Only 34 MAX simulators existed worldwide. That limited global capacity created a potential bottleneck affecting how quickly airlines could retrain their pilots.

- Training 5,000 pilots for ten simulator hours each would require roughly two months under ideal conditions. This illustrative calculation assumed that all 34 simulators operated continuously, 24 hours a day, seven days a week.

- The actual training delay could be considerably longer. More than 5,000 pilots might require retraining, the FAA could mandate more than ten hours, and simulators could not realistically operate at perfect efficiency.

- Airlines that owned their own MAX simulators would have a significant advantage. They could prioritize their pilots rather than compete with other airlines for limited training slots.

- South Korea’s Eastar Jet was identified as an airline without its own MAX simulator. It would therefore need to obtain training capacity from another operator or a commercial training provider before restoring its aircraft to service.

- Smaller airlines were expected to face longer simulator queues. Independent training centers had commercial incentives to prioritize large customers such as American Airlines over smaller operators such as Eastar Jet.

- Even major airlines were expected to send pilots internationally for simulator training. With equipment scattered across the world, airlines were searching for available training hours wherever they could find them.

- Fiji Airways owned a MAX simulator in Fiji. This gave the airline the ability to train its own pilots relatively quickly and created an opportunity to earn substantial revenue by offering simulator time to other airlines.

- Simulator capacity was also available in locations including Iceland and Panama. Airlines were examining international training options, and limited supply increased the commercial value of available simulator hours.

- The precise simulator bottleneck depended on the FAA’s final training requirements. Until the Flight Standardization Board completed its work, airlines could not determine their exact retraining needs.

- The FAA’s airworthiness directive would establish the formal conditions for returning the MAX to service. It would specify the aircraft modifications and pilot training that individual airlines needed to complete before resuming operations.

- Issuing the airworthiness directive would mark the beginning of substantial operational work, not its completion. Each airline would remain responsible for bringing its aircraft and pilots into compliance.

- Most of the 387 previously operating aircraft had not been maintained to normal daily operating standards during storage. Keeping every grounded aircraft fully ready for immediate commercial use would have been prohibitively expensive.

- Every stored MAX aircraft would require extensive inspections and system testing. Mechanics would need to verify that components and systems remained functional after the prolonged period of inactivity.

- Grounded aircraft would also require deep cleaning and updated software. These tasks formed part of the work needed to make individual aircraft safe and operational again.

- Preparing each grounded aircraft for service could take up to two weeks. The exact effort would depend on the aircraft’s condition and the modifications required.

- Airlines were expected to reassign mechanics to accelerate the MAX’s return. Once regulatory timing became clearer, operators could concentrate maintenance staff on restoring grounded aircraft.

- Other aircraft maintenance could be delayed as a consequence. Airlines might postpone heavy maintenance on their existing fleets to devote more mechanics and facilities to the MAX.

- Boeing faced an even more extensive process for approximately 400 undelivered aircraft. Although largely assembled, these jets still required significant completion work before they could be handed over to customers.

- Clearing Boeing’s undelivered MAX backlog was expected to take approximately one year. Regulatory approval would therefore not translate into the immediate delivery of every aircraft already manufactured.

- Airlines would need to rebuild the MAX into their flight schedules. Returning an aircraft to technical readiness would not automatically mean it could be assigned to commercial flights.

- A summer return could accelerate the aircraft’s commercial deployment. Summer was generally the industry's more profitable travel season, giving airlines an incentive to restore capacity quickly and possibly schedule additional flights.

- A return during a quieter travel season could delay full deployment. Airlines might have less immediate demand for the aircraft, while established flight schedules were sometimes planned years in advance.

- Passenger acceptance remained one of the largest uncertainties. A commissioned survey found that 70% of American travelers said they would avoid the 737 MAX even after it received regulatory approval.

- Previous aircraft groundings had not produced serious, lasting passenger boycotts of the affected models. This historical precedent suggested the MAX could eventually regain public acceptance, although the circumstances of its grounding were different.

- The MAX grounding attracted an unusually high level of media attention. Unlike many previous aircraft safety incidents, it had become a widely recognized international controversy.

- Modern airline booking systems gave passengers greater control over aircraft selection. Online bookings often displayed the aircraft type, allowing customers to choose alternatives to the MAX.

- Earlier generations of passengers generally had less information about aircraft models. When bookings were commonly arranged through travel agents, customers often did not know what type of aircraft they would fly.

- Greater access to aircraft information could make a MAX passenger boycott more practical. Customers who distrusted the aircraft could identify and avoid it before purchasing tickets.

- Social media introduced an additional risk to passenger confidence. The video suggested that a viral recording of an anxious passenger discovering they were aboard a MAX could spread concern and influence other travelers.

- Boeing was developing a passenger-reassurance strategy covering the entire journey. Its preparations addressed concerns arising during booking, at the airport, and aboard the aircraft.

- Boeing planned to monitor social media for passengers expressing anxiety about the MAX. If someone posted concerns from an airport or during a flight, the company intended to respond digitally.

- Boeing also planned to alert flight crews about passengers publicly expressing concern. This would allow airline personnel to identify and potentially assist anxious travelers during their journey.

- Boeing intended to distribute printed aircraft-safety information cards. Employees would provide these to concerned passengers, explaining the aircraft’s safety and the modifications made after the grounding.

- Boeing planned explanatory videos about the MAX’s safety improvements. These would give passengers a more detailed account of the changes and the aircraft’s return to service.

- A major public-information campaign was expected to accompany the aircraft’s return. Boeing would need to address public fears at scale rather than rely exclusively on regulatory approval.

- Passenger confidence directly affected Boeing’s ability to sell the MAX. If travelers refused to fly on the aircraft, airlines would have less reason to purchase or operate it.

- The MAX was central to Boeing’s commercial aircraft business. Its importance as a high-volume, revenue-generating product made the successful return to service crucial to the company's financial position.

- The return to service depended on several separate processes succeeding. Certification, pilot retraining, aircraft modifications, maintenance, deliveries, airline scheduling, and passenger acceptance all had to be managed.

- A failure or significant delay at any stage could disrupt the wider recovery. Approval of a technical fix would not eliminate shortages in simulator capacity, aircraft preparation resources, or commercial demand.

- The recovery plan remained a forecast rather than a guaranteed outcome. Previous missed deadlines showed how difficult it was to predict the MAX’s return, and the video concluded that Boeing faced exceptionally high stakes in restoring both the aircraft and public trust.