Wendover’s $6 Billion Tejon Claim Has a Missing Calculation
Wendover Productions identifies a potentially serious scandal in California's high-speed rail project: the state may have inflated the cost of the shorter Tejon Pass route to avoid confronting a powerful landowner and justify sending the railway through Palmdale.
But the video makes its strongest accusation without showing the calculation behind it. It claims that avoiding Tejon Ranch inflated construction costs by as much as $6 billion, then suggests the alleged political arrangement between Jerry Epstein and Michael Antonovich almost certainly had some truth to it.
I investigated the engineering record, contemporary reporting, political campaign, and the actual Marina del Rey lease documents. The evidence establishes significant political influence and a legitimate question about how the Tejon alternative was evaluated. It does not establish the $6 billion loss or prove the alleged exchange.
The difference matters.
1. The route decision was more complicated than one political vote
The direct Interstate 5 route was not an obscure alternative invented by later critics.
A 1999 final report, examined in a 2022 investigation by The New York Times, identified the I-5 corridor as the preferred option. The Palmdale alternative added approximately 41 miles and was estimated to increase costs by 16%, potentially equivalent to as much as $8 billion in current costs.
But the political and technical arguments changed as the planning progressed.
In September 2004, the California High-Speed Rail Authority board tentatively favored Palmdale. The competing route was approximately 35 miles shorter and saved around 10 minutes, but Authority officials argued that Palmdale would cost less, damage fewer parklands, and involve lower seismic risks.
Importantly, this was only a straw vote. The board acknowledged that members had not had enough time to review all the reports, including more than 2,000 public comments. A formal decision was still scheduled for December.
The Los Angeles Times documented the decision and its qualifications in September 2004.
The subsequent 2005 environmental review provided a more substantial technical explanation.
The Authority and Federal Railroad Administration considered six broad corridors. Four Interstate 5 alternatives were eliminated because they required long tunnels through seismic zones, crossing or running alongside active faults.
The remaining I-5 alternative, designed around a 3.5% maximum grade, was compared with the Antelope Valley route.
The resulting comparison was significant:
- Antelope Valley required approximately 13 miles of tunneling.
- The I-5 alternatives required approximately 23 miles.
- The longest Antelope Valley tunnel was approximately 3.4 miles.
- The I-5 alternatives included two tunnels exceeding five miles.
- Antelope Valley was approximately 35 miles longer but was estimated to be slightly cheaper.
The Authority also identified potential impacts on Fort Tejon Historic Park, Angeles and Los Padres National Forests, Hungry Valley State Recreation Area, and Pyramid Lake along the I-5 alternatives.
These findings appear in the Authority's May 2021 Final Environmental Impact Report, Chapter 2, which reproduces the earlier corridor analysis.
This does not prove the Authority's engineering assumptions were correct. It does establish that the tunnel problem was not invented solely to protect a real estate developer. Seismic conditions, parkland, tunnel lengths, and construction difficulty were genuine elements of the official comparison.
Wendover should have explained this distinction much more carefully.
2. California actually reconsidered the Grapevine route
There is another important omission.
In May 2011, the Authority's board unanimously agreed to reopen the Interstate 5 alternative for further study.
This happened after growing concerns about the costs and engineering complexity of the Palmdale route. The Authority was not simply defending a decision made years earlier; it was reconsidering it.
The contemporary reporting is particularly revealing.
Tejon Ranch opposed the revived I-5 proposal because its planned development included a $75 million investment in a proposed mountain community and business park. The company argued that a railway could damage those investments.
The Los Angeles Times documented the renewed route debate on May 6, 2011.
The subsequent study produced a more complicated result.
A January 2012 report found:
- The Grapevine route was slightly less expensive.
- Its travel-time advantage was approximately three to five minutes, rather than the initially estimated 10–12 minutes.
- Both alternatives presented similar earthquake risks.
- Palmdale required less tunneling than originally anticipated.
- Palmdale offered fewer environmental impacts and greater flexibility through the mountains.
The researchers were from Parsons Brinckerhoff and Hatch Mott MacDonald, two of the project's main contractors. This is an important qualification: the comparison was not an independent external audit.
The Authority ultimately reaffirmed its preference for Palmdale.
The Los Angeles Times reported the findings on January 10, 2012.
Wendover mentions the Authority's cost argument, but does not give readers enough of this subsequent history to understand what was actually reconsidered, what the new study found, and who conducted it.
3. The direct Tejon Ranch alternative deserves investigation
Here, the criticism becomes considerably stronger.
A contemporary technical critique by Alon Levy, published on January 11, 2012, identified a potentially important weakness in the Authority's Grapevine study.
Levy argued that the cheapest and fastest I-5 alignment would have crossed Tejon Ranch directly. Instead, the Authority examined a more expensive and slower alternative through Lebec, avoiding the significant property acquisition and scheduling risks associated with bisecting the ranch.
His analysis identified base estimates of approximately $13.5 billion for Grapevine versus $15 billion for Palmdale. He argued that risk adjustments obscured the difference.
In a subsequent comment, he suggested that a more rational direct alignment through Tejon Ranch might reduce the Grapevine estimate to approximately $11.5 billion.
That is a potential $2 billion saving against his cited base estimate, not an independently established $6 billion saving.
Crucially, Levy also questioned how difficult it would be to obtain permission for the direct alignment.
His original analysis is available at Pedestrian Observations.
This is the distinction Wendover needed to make.
There are three separate questions:
- What would the I-5 route cost if it avoided Tejon Ranch?
- What would it cost to acquire the necessary property and build directly through the ranch?
- Would the additional legal, environmental, and construction risks make that direct route economically preferable?
The second option was not developed to the same engineering detail as the established alternatives.
That is a legitimate criticism of the Authority's planning process. A potentially cheaper route was not subjected to a sufficiently mature, comparable evaluation.
But an unbuilt alternative cannot simply be assigned a hypothetical saving and treated as a demonstrated public loss.
4. Where did the $6 billion figure come from?
This is the weakest part of Wendover's argument.
The narration says:
"Independent analysis has suggested that this inflated cost by as much as $6 billion."
It does not identify the analyst, the study, the original cost estimate, the price year, or the engineering assumptions behind the calculation.
There are several different historical estimates that should not be confused.
The 1999 report, as described by the New York Times, estimated that Palmdale would increase costs by 16%.
The Authority's 2005 comparison subsequently concluded that the longer Palmdale alignment could actually be slightly cheaper because of reduced tunneling.
The January 2012 Los Angeles Times report also mentioned an original Grapevine estimate of $6.6 billion. But that was an early estimate for the alternative, not a measured $6 billion surcharge caused by avoiding Tejon Ranch.
These figures concern different studies, design assumptions, and stages of project development. They cannot simply be subtracted from one another.
The video never reconciles them.
I would not publish the $6 billion as an established saving without seeing the underlying calculation.
The appropriate investigation would compare the direct Tejon alignment, the proposed tunnel and bypass alignment, and Palmdale using the same construction scope, price year, engineering standards, land acquisition assumptions, and risk adjustments.
Until that happens, the $6 billion remains an unsupported figure in the video's narration.
5. Palmdale's political campaign was more substantial than the video reveals
Wendover concentrates on Antonovich and Epstein. It overlooks a much more thoroughly documented political campaign.
In August 2004, the Los Angeles Times reported that Palmdale had spent more than $500,000 on lawyers, public relations specialists, economic studies, and geological consultants to persuade state officials to select its preferred alignment.
The money came from sales taxes earmarked for public transportation.
The city's consultants argued that the Grapevine route would cost more and take longer because weak rock would require additional tunnel stabilization.
Palmdale also assembled support from the Metropolitan Transportation Authority, several members of Congress, Los Angeles, and Chowchilla.
The mayor openly declared that the city was prepared to spend more to win the alignment.
This campaign was documented by the Los Angeles Times on August 9, 2004.
This is important because it establishes that the route decision was subject to sustained, organized political pressure.
The city had an obvious economic interest in securing a station. It wanted development, employment, commuters, and investment.
That does not make its arguments false. But its consultants' cost estimates should not be confused with independent assessments.
The video could have given readers this documented political history instead of relying so heavily on one alleged private arrangement.
6. The Epstein–Antonovich arrangement: real interests, unproven exchange
The alleged arrangement deserves serious scrutiny.
The New York Times investigated the relationship in October 2022.
Art Bauer, the former chief staff member of the State Senate Transportation Committee, alleged that Jerry Epstein supported Antonovich's Palmdale proposal in exchange for support for his Marina del Rey lease extension.
Bauer described the alleged arrangement in unusually direct terms:
"If I get my lease, you get my vote."
He also claimed Epstein's lobbying persuaded other rail board members.
Antonovich denied that there was any connection between Epstein's lease interests and his support for Palmdale.
The New York Times investigation records both the allegation and Antonovich's denial.
The public records establish that the financial interests were real.
An October 2006 Los Angeles County report identifies Epstein among the original lessees of Marina del Rey's Del Rey Shores properties.
The proposed arrangement was substantial:
- A 39-year lease extension option, extending the term to March 2061.
- Replacement of 201 existing apartments with 544 apartments.
- An $11.05 million credit for the lessee, justified by the County as recognition of construction costs and affordable housing.
- A minimum $1 million extension fee.
- An appraisal that County staff said showed returns equivalent to or greater than fair market value.
The County report also describes an invitation seeking competitive proposals and an evaluation committee that recommended proceeding with negotiations.
The original County lease report, dated October 19, 2006, contains these details.
There is an additional chronological detail.
In December 2009, Epstein's chief of staff, David Levine, told the County Board of Supervisors that the lease project had been in progress since 2000. He confirmed that the Board approved the lease extension agreement in December 2006.
The official Board meeting transcript records his statement.
The lease negotiations therefore overlapped the period when the railway route was being decided. The final extension option, however, was approved after the 2004 straw vote and the 2005 environmental selection.
This chronology neither proves nor disproves an earlier political promise.
The County documents establish the commercial transaction and its formal approval process. They do not establish that Antonovich exchanged political support for Epstein's railway vote.
That is precisely where the investigation must distinguish documented financial interests from an alleged private bargain.
Wendover does not do that adequately when it concludes that the story "almost certainly has some truth to it."
7. What the investigation should actually establish
The strongest case against the California High-Speed Rail Authority is not that Palmdale was unquestionably the wrong route.
It is that the public never received a sufficiently transparent, independently verified comparison of the cheapest feasible direct Tejon alignment against the alternatives.
The next investigation should establish:
- Who decided that the direct Tejon Ranch alignment would not receive detailed engineering?
- What were the exact land acquisition and legal risks?
- How were tunnel costs and seismic risks calculated?
- Why were the risk adjustments applied in the 2012 comparison?
- What would a direct alignment have cost if the state exercised its eminent-domain authority?
- Did political lobbying or private financial interests influence which alternatives were considered?
Those are answerable questions. They deserve original documents, engineering calculations, board records, and independent technical scrutiny.
Closing verdict
Wendover identifies the right place to investigate, but its strongest accusation outruns its evidence.
The Palmdale decision involved documented political lobbying, a powerful landowner with substantial property interests, and a railway board member involved in a major lease negotiation. The Authority also had documented engineering and environmental reasons for its preferred alignment.
The unresolved issue is whether the Authority gave the cheapest feasible Tejon Ranch route a fair engineering comparison, or allowed the anticipated political and legal difficulties of confronting the landowner to determine the options it was willing to study.
That is a serious institutional failure if established.
But $6 billion is not a finding simply because an alternative might have been cheaper. And an alleged exchange is not proven because the people involved had overlapping interests.
Wendover has identified a credible potential scandal. It has not completed the investigation needed to establish its most damaging claims.
The public deserves to know whether California rejected a cheaper railway, or whether it rejected a cheaper railway on paper that was never realistically engineered. That is the $6 billion question.
References
- What Went Wrong With California High Speed Rail — Wendover Productions. The original work under review.
- Bakersfield to Palmdale Final EIR/EIS, Chapter 2: Alternatives — California High-Speed Rail Authority, May 2021. Documents the 2005 corridor screening, seismic constraints, tunnel comparisons, and estimated cost advantages.
- CEQA Findings of Fact and Statement of Overriding Considerations — California High-Speed Rail Authority, August 2021. Explains why the Authority rejected I-5, including the acknowledged travel-time and ridership disadvantages of Palmdale, and confirms the 2011 reconsideration.
- Palmdale On Board With High-Speed Rail Plan — Los Angeles Times, August 9, 2004. Documents Palmdale's publicly funded lobbying campaign and its use of legal, public relations, geological, and economic consultants.
- Antelope Valley on Fast Track — Los Angeles Times, September 23, 2004. Records the preliminary board vote, the unreviewed public comments, and the technical arguments for Palmdale.
- High-Speed Rail Planners Revive Grapevine Route — Los Angeles Times, May 6, 2011. Establishes that the Authority reopened the I-5 alternative and documents Tejon Ranch's development interests.
- Planners Want to Discard Grapevine Route for Rail Project — Los Angeles Times, January 10, 2012. Reports the second route comparison, the contractors involved, the reduced travel-time advantage, and the earlier $6.6 billion estimate.
- Update on the Grapevine — Pedestrian Observations, Alon Levy, January 11, 2012. Presents a contemporary technical challenge to the Authority's route assumptions and a hypothetical cheaper alignment through Tejon Ranch, while acknowledging unresolved permitting risks.
- How California's Bullet Train Went Off the Rails — The New York Times, Ralph Vartabedian, October 9, 2022. Reports the 1999 route comparison and the Epstein–Antonovich allegation, including Antonovich's denial.
- Option for Amended and Restated Lease: Del Rey Shores — Los Angeles County Department of Beaches and Harbors, October 19, 2006. Provides the original lease terms, 39-year extension option, financial credits, appraisal, and evaluation process.
- Board of Supervisors Meeting Transcript — Los Angeles County, December 15, 2009. Contains Epstein representative David Levine's statement confirming that the lease process began in 2000 and the extension agreement was approved in December 2006.
Separate the 2005 and 2012 route comparisonsReplace the $6 billion opening with the strongest findingLabel Alon Levy’s estimate as a hypothesis